A 1 MW photovoltaic installation together with the necessary accompanying infrastructure.
Object
Construction of a 1 MW photovoltaic installation together with the necessary infrastructure, including a 15 kV connection to the power grid.
Scope
Construction of a 1 MWp photovoltaic farm: Comprehensive execution of the investment, including the multi‑disciplinary building and technical design with obtaining the building permit, construction and installation works such as site preparation, fencing, surface reinforcement, installation of the PV panel support structures, installation of PV panels and inverters, DC and AC cabling, installation of a 15/0.4 kV transformer station, connection to the 15 kV grid, testing and commissioning of the telemechanics and control system integrated with the operator’s dispatch system.
Date
2023-2025